From decision to go-live

Not an implementation project but a structured sequence with clearly assigned tasks.

Updated:

In short

The standard Door James rollout is built for speed: as a planning assumption around four weeks per first location, with further locations running in parallel. The sequence covers 15 steps from kick-off through SSO setup, capture of floor plans and assets, configuration and approval to training and go-live. There is no implementation fee for the standard rollout.

Timeline
around four weeks per first location
Parallel
further locations at the same time
Cost
no implementation fee
Afterwards
self-administration in the Admin Panel

Why it is not a classic implementation project

Door James is a standardized product. The rollout therefore consists not of development but of data capture and configuration. That shifts the critical path: the pace is set not by the software but by the availability of your location data.

What you can prepare before the start

Three things noticeably shorten every rollout. First, current floor plans in a usable format. Second, a complete list of bookable resources with numbering, type and equipment. Third, an appointment with whoever approves Entra ID registrations in your organization. Clarifying those three before the kick-off usually saves one to two weeks.

After go-live

We stay close in the first weeks, because that is when the typical adjustments come up: sharpening rules, renaming areas, tuning quotas. After that, responsibility moves to your administrators as planned – and the only recurring task is to look at the reports.

How it works

  1. 1

    Kick-off and demo

    Shared understanding of goals, locations and scope; demonstration of the platform for everyone involved.

  2. 2

    Align stakeholders

    Involve project owners, location owners, IT, data protection and employee representatives early.

  3. 3

    Define module scope

    Which modules are activated, organization-wide and per location?

  4. 4

    Set up identity

    OIDC connection to Entra ID or another provider, groups and permitted domains.

  5. 5

    Capture floor plans and office data

    Floor plans, addresses, opening hours, reception details, banner images.

  6. 6

    Provide the asset list

    Bookable resources in an agreed spreadsheet – numbering, type, equipment, restrictions.

  7. 7

    Build the location

    Areas, zones and assets are created and placed on the floor plan.

  8. 8

    Configure privacy and visitors

    Deletion periods, anonymization, location-specific notices, visitor workflows and questionnaires.

  9. 9

    Enable integrations

    Outlook room calendars, Teams app and further connections, where in scope.

  10. 10

    Approve the location

    Location owners review the configuration and approve it.

  11. 11

    Order stickers

    QR code stickers for check-in, if used, and placement on site.

  12. 12

    Admin training

    Training for administration and reception roles, handover of manuals.

  13. 13

    Inform users

    Communication to the workforce with templates, videos and notes on the rules.

  14. 14

    Go-live

    Release for all users at the location.

  15. 15

    Follow-up

    Support and customer success for the first weeks, then self-administration.

Frequently asked questions

What typically delays a rollout?

Almost always the same three things: missing or outdated floor plans, an incomplete asset list, and scheduling with IT for the identity connection. All three can be prepared before the project starts.

Can we roll out several locations at once?

Yes. After the first location the sequence is established; further sites run in parallel, depending on how quickly location data arrives.

Who maintains the locations afterwards?

Your location and organization administrators in the Admin Panel. That is exactly what the role model is designed for.

Do we need a project team?

One project owner plus one responsible person per location is usually enough. A larger team is not necessary; clear ownership is.

Plan the rollout with someone who has run one

Pilot floor, data import, works council, who signs off what. Thirty minutes on your plan is cheaper than discovering the order was wrong.

30 minutes, Microsoft Teams, no preparation needed